Key facts

  • Approved: $36.24M revenue bonds via state SWIFT loan1
  • Leander’s total Phase 2A draws: $72.48M1
  • Plant capacity: 41.9 → 64.2 million gallons a day1
  • New finish date: Oct. 20281

The 30-second version

Leander shares a water plant with Cedar Park and Round Rock (BCRUA). The plant is growing. Only Leander and Round Rock pay for this expansion; Cedar Park is not part of it. Leander pays its part with low-rate state loans, paid back from water bills, not taxes, so no vote is needed. On Oct. 15 the council approved the last $36.24M draw. Repayment totals about $56.7M, about $2.2M a year.1 Crews had to dig deeper after finding foreign material, so the finish date is expected to move from June to Oct. 2028.1

Also on the consent agenda: a $1.29M cybersecurity purchase and acceptance of $8.6M of new sewer-plant infrastructure.1

The other side

  • State water loans cost less than regular bonds, which helps keep water bills lower over time.
  • The expansion adds treatment capacity to the plant.1
  • The delay comes from extra digging work, not from a money problem the packet shows.

Questions to ask

  • How will the city report progress on the water plant’s finish date?
  • When will the city report the final cost of the extra digging?

Changes to this page

  • Nov. 2, 2026: Replaced an unsourced claim about future water limits with what the packet says the expansion does. Removed a pointer to an internal file.
  • Nov. 2, 2026: Added questions to ask.

What you can do or watch next

  • Watch for the official minutes, which will confirm the vote count.
  • Watch for the next BCRUA update on the Oct. 2028 finish date.
  • You can speak at any council meeting during public comment, or email council members.

What we still don’t know

  • Whether the new finish date for the water plant will hold.
  • What the extra digging will cost in the end.

Footnotes

  1. Council packet, Oct. 15, 2026, items 17 and consent. CivicClerk. Video: Swagit. ↩ ↩2 ↩3 ↩4 ↩5 ↩6 ↩7 ↩8